“Rooms Tbilisi” Hotel
“Rooms Tbilisi” Hotel 2015
Challenges:
❖ Was simple, nice project, without special challenge.
Works done:
◆ Fire detection System:
– Smoke and heat detectors;
– Canal airduct smoke detectors;
– fire alarm buttons;
– FCP with remote control panel;
– დამწნეხი და ბოლის გამწოვი ვენტილატორები;
– smoke exhaust dampers;
– 8 fire zone separation doors
– Boiler room CO leakage detection;
◆ Voice evacuation system:
– Loudspeakers
– 2 power amplifiers;
– Audio control module;
– Enunciation panel;
◆ Building Automation System. Automation of. Automation of:
– HVAC – AHUs, FCUs;
– DHW plant control;
– Water pressurization station – 3 pumps;
– General and Fire suppression water reservoir control and monitoring;
- – General exhaust fans;
– Electrical main distribution plant monitoring;
– Fire suppression plant monitoring;
– Disabled person call system:
– call stations;
– Call control panel