Challenges:

Establishing shared control network , with central monitoring and control center, for energy efficient and comfortable environment. From the other hand, building stable operation was alsow an aim;. Building Automation System. Automation of Building Automation System. Automation of:

Works performed:

Building Automation System. Automation of:

HVAC – AHUs, pipe FCUs;

Chillers – 600KW each

Water boilers – 1000KW each;

Chilled water circulation plan;

Heating water circulation plant;

Open type cooling towers;