Challenge(s):

❖ Establish single BACnet IP automation network, for 4 blocks of the shopping center;

Works performed:

◆ Building Automation System Automation of:

8 AHUs, 22 RTUs, 33 FCUs, 21 exhaust fans;

3 water boilers, 1,5MW each

 Hot water circulation plant on 15 pumps, 12 motorized valves;

DHW production plant, 3 water boilers, 1,5 KL each, 7 pumps; each, 7 pumps

4 air to water chillers, 0,6 MW each;

A dry cooler;

Chilled water circulation plant, 18 pumps, 11 motorized valves;

Floor heating plant, a 3-way valve, 4 motorized valves

◆ Plumbing system automation:

4 water pressurization stations, 3-5 pumps each;

2 waterfall plants, with 4-5 water pumps;

3 Water reservoirs, on 20-30 m3 storage;

3 Fire suppression stations, 9 pumps;

◆ Smoke control system:

60 fire dampers;

34 smoke dampers

22 pressurization and exhaust fans;

◆ Water metering system:

51 water meters, connected to centralized metering system via M-bus network;